The Challenge
Earned value analysis compares the work planned, the work done and the money spent, so a contractor can see early whether a project is running over budget or behind schedule. The company had two earned value sheets meant to do this, but they had to be filled in by hand from their budget files, and the owner knew what the sheets should show without having the time to make them work. After a phone call and a look at the sheets, we proposed a tool built around the company's own budget export.
The Earned Value Tool
The first project was quoted at 8 hours:
- Data set-up. A button imports the newest budget file into a budget tab, and a list of activities and phases drives the drop-downs.
- Activity tracking. The user adds a stage and an activity, and the original and actual figures for that activity fill in from the budget automatically.
- Earned value metrics. Days, percentage complete, budget at completion, planned value, actual cost and the to-complete performance index sit alongside calculated cost per day and earned value.
The owner pasted the scope into a document, added comments in red and approved it the next morning, along with the company's accounting codes.
Pulling More From the Budget
A week later we agreed a second round, quoted at 4 hours, so that fewer figures had to be typed in:
- overhead and profit pulled to the top for the original and revised budgets, and left out of the activity rows;
- revised budget figures brought in directly, with a total and a percentage difference from the original;
- budget at completion and actual cost taken from the budget file instead of entered by hand;
- cost per day based on the revised budget, planned value calculated from the planned percentage complete, and the performance index calculated automatically;
- two editable rows at the top for project details.
Estimates and Tracking Files
Two months later the company asked for changes to three construction tracking files. The estimate sheet exported from its construction management software was rebuilt to run from a macro rather than fragile formulas: mark-up columns that were no longer needed were removed, the summary moved to the top, and units, unit cost, overhead, profit, extended cost and line item totals were brought in from a new estimate tab that imports the budget. That project was also quoted at 8 hours, and we went on to link the work breakdown structure to the earned value tool and help with further changes later in the year.
The Result
The company could see each project's health from current figures without retyping its budget.
Why Excel?
The company's budget and estimate files already came out of its systems as spreadsheets. Earned value calculations are straightforward formulas once the data is in the right place, so automating the import in Excel was quicker and cheaper than adopting a project controls package.
Could This Work for Your Business?
The same approach suits contractors, engineers and project-based businesses that want earned value or cost forecasting from their existing budgets. Send us a sample budget export and we can usually get back to you with a fixed price within 24 hours.
Questions About Earned Value Tracking in Excel
Can Excel calculate earned value automatically?
Yes. Planned value, earned value, actual cost and the performance index were calculated for each activity.
Can it import our budget file?
Yes. A button loaded the newest budget, and activity figures filled in from it.
Can overhead and profit be handled separately?
Yes. They were shown at the top and left out of the activity rows.
Can estimates link to the same budget?
Yes. The estimate sheet was rebuilt to pull its figures from the imported budget.
What does an earned value tool cost?
We quote a fixed price after a free scoping call, and you only pay once you are happy with the finished work. At our current rates, a similar project would typically cost $1,200–$1,500.